bizSAFE
May 2011
Achieved BizSAFE Level 3.
|
JUNE 2011
June 2011
Signed on exclusive master distributor agreement with Gamatronic. Website-www.gamatronic.co.il.
|
Official Showroom
Nov 2011
Official opening of EngHoe Showroom, presenting Gamatronic Modular UPS system.
|
New Products
Dec 2011
Sunlight and Intellibatt in replica watches our showroom.
|
JAN 2012
Jan 2012
Intellibatt Appointments as Approved Service Provider (ASP) and Exclusive Distributor.
Launch of ENG HOE UPS Systems (1kVA to 10kVA).
|
Announcement
Apr 2012
Intensive Training by Intellibatt for rolex replica local Engineers
|
Official launch
Oct 2012
Official launch of IntelliBatt UPS and Battery Monitoring for the Singapore & APAC markets
|
JUNE 2013
Intellibatt change of name to canara www.canara.com
|
JUNE 2013
The official count down of canara installation from official launch in OCT 2012 is 6540 nodes.The replica rolex company expects to hit 10,000 nodes by year end 2013.
|
SEP 2013
After 9months of inconveniences, we have finally completed our A&A works transforming our two storey building to a three storey building.
This has increased our gross working area to 15000 Sq.ft.more
|
MAR 2014
Mar-2014 Canara node installation 234. From Oct-2012 total nodes installation and monitoring 6774. Additional monitoring of 20,587 batteries have being connected to our Canara web based global Monitoring Centre.
|
bizSAFE
April 2014
Achieved BizSAFE Level 4. fake watches
|
AUG 2014
From April to Aug-2014 Canara node installation 702. From Oct-2012 total nodes installation and monitoring 7476. Additional monitoring of 20,587 batteries have being connected to our Canara web based global Monitoring Centre.
|
DEC 2014
Dec-2014 Canara node installation 234. From Oct-2012 total nodes installation and monitoring 7710. Additional monitoring of 20,587 batteries have being connected to our Canara web based global Monitoring Centre.
|
JAN 2015
Jan-2015 Canara node installation 234. From Oct-2012 total nodes installation and monitoring 7944. Additional monitoring of 20,587 batteries have being connected to our Canara web based global Monitoring Centre.
|
MAR 2015
Mar-2015 Canara node installation 198. From Oct-2012 total nodes installation and monitoring 8142. Additional monitoring of 20,587 batteries have being connected to our Canara web based global Monitoring Centre.
|
MAY 2015
May-2015 Canara node installation 468. From Oct-2012 total nodes installation and monitoring 8610. Additional monitoring of 20,587 batteries have being connected to our Canara web based global Monitoring Centre.
|
JUL 2015
Jul-2015 UPS batteries replacement From Mar-2015 total batteries replacement 6126.
|
OCT 2015
Oct-2015 UPS batteries replacement 102. From Mar-2015 total batteries replacement 6228.
|
AUG 2016
Aug-2016 Canara node installation 616. From Oct-2012 total nodes installation and monitoring 9226.
|
NOV 2016
Nov-2016 Canara node installation 272. From Oct-2012 total nodes installation and monitoring 9498.
|
DEC 2016
DEC-2016 Generator starter batteries replacement 56. From Mar-2015 total batteries replacement 6284.
|
JAN 2017
JAN-2017 UPS batteries replacement 136. From Mar-2015 total batteries replacement 6420.
|
AWARD
JUN 2017
Achieved 5 years MSA award with Multinational Data Centre
|
SEP 2017
SEP-2017 Repaired 3000 MVA tranformer oil leakage.
|
NOV 2017
NOV-2017 UPS batteries replacement 1,700.From Mar-2015 total batteries replacement 8,120.
|
DEC 2017
DEC-2017 Generator starter batteries replacement 40. From Mar-2015 total batteries replacement 8,160.
|
MAR 2018
MAR-2018 Repaired 3000 MVA tranformer oil leakage.
|
APR 2018
APR-2018 Generator Starter batteries replacement 44.From Mar-2015 total batteries replacement 8,204.
|
MAY 2018
MAY-2018 UPS batteries replacement 776.From Mar-2015 total batteries replacement 8,980.
|
MAY 2018
MAY-2018 Generator Starter batteries replacement 36.From Mar-2015 total batteries replacement 9,016.
|