Ministry/Dept |
Project Title |
Project Duration |
UPS Equipment |
Keppel Seghers Engineering /LTA |
KPE/C413 |
2003 to 2009 |
18X100KVA
12 x 150KVA
22 x 200KVA
4 x 250KVA
4 x 300KVA |
Description: Supply, delivery, installation, integration, testing and commissioning of uninterruptible power supply system to 6 ventilation buildings. The Location of each ventilation building is 1.5 km from each other. UPS systems at each ventilation building are connected via optic fiber, through which they are remotely monitored and controlled by the control center located at VBC, and the backup center at VBD. The UPS are equipped with Sunlight battery.


1. Ventilation Building A and Ventilation Building B
2. Ventilation Building C and Ventilation Building D
3. Ventilation Building E and Ventilation Building F
|
|